5 Cy-Fair road project updates from Harris County Precinct 3

Sign in or sign up to leave a comment
Sign Up

1. Grant Road widening

Project: Harris County Precinct 3 will widen Grant Road from a two-lane roadway to a four-lane divided concrete boulevard in phases: from Spring Cypress Road to Shaw Road (Phase 2), from Shaw Road to Telge Road (Phase 3), and from Telge Road to Cypress Rosehill Road (Phase 4). Grant Road was widened from Lakewood Forest Drive to Louetta Road between 2017-2019.

Update: This project is in the study phase and is expected to start going out to bid in 2026.

  • Timeline: Early 2026 bid (Phase 2), late 2026 bid (Phase 3), late 2027 bid (Phase 4)
  • Cost: $10.5 million (Phase 2), $6.5 million (Phase 3), $14 million (Phase 4)
  • Funding source: Harris County Precinct 3

2. North Eldridge Parkway widening

Project: Harris County Precinct 3 will widen North Eldridge Parkway to a four-lane divided concrete boulevard from south of Pine Drive to south of Lakewood Meadow Drive. The project is located near Cypress Park and the confluence of Cypress Creek and Little Cypress Creek.

Update: This project is in the design phase.

  • Timeline: Late 2025 bid
  • Cost: $5 million
  • Funding source: Harris County Precinct 3

3. Cypress North Houston Road widening

Project: The two-lane roadway will be widened to a four-lane divided concrete boulevard from Jones Road to Perry Road.

Update: This project is in the design phase.

  • Timeline: Early 2026 bid
  • Cost: $16 million
  • Funding source: Harris County Precinct 3

4. Greenhouse Road tunnel under Hwy. 290

Project: Officials will construct an underpass beneath Hwy. 290 from Mound Road to north of Hwy. 290, extending Greenhouse Road to Skinner Road.

Update: This project is in the design phase.

  • Timeline: Early 2026 bid
  • Cost: $45 million
  • Funding sources: local, state and federal

5. Greenhouse Road bridge over Cypress Creek

Project: Harris County Precinct 3 is completing a four-lane boulevard section south of Mound Road.

Update: This project is in the construction phase.

  • Timeline: First quarter 2025 completion
  • Cost: $8.7 million
  • Funding source: Harris County Precinct 3
By Danica Lloyd

 Editor

Categories: Home BuyingHome SellingGeneral
Favourites If you enjoyed this post, please consider sharing it with others.
Sign in or sign up to leave a comment
Sign Up
To post a comment on this blog post, you must be an HAR Account subscriber, or a member of HAR. If you are an HAR Account subscriber or a member of HAR, please click here to sign in. If you would like to create an HAR Account account, please click here.
Disclaimer: The views and opinions expressed in this blog are those of the author and do not necessarily reflect the official policy or position of the HRIS.

View Q&A Posts in Home Buying , Home Selling , General